NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING.

 System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.

DON GUILLO RESTAURANT
02551 DELTA DR

Review DateStatusComment(s)
5/22/2020 FYI*****(STANDARD COMMENT) This project is: Don Guillo, 2551 Delta Dr: interior remodel - expansion of tenant space Date of Plans:3/25/2020 You can access our web site for the latest fire department plan review comments: www.coloradosprings.gov search for Plan and Construction Review.
FYI(STANDARD COMMENT) IMPACT TO EGRESS AND/OR FIRE PROTECTION SYSTEMS Egress components and fire protection systems that may be negatively impacted by your scope of work will be required to comply with the currently adopted fire code. As an example, if your work increases the occupant load of a space, the existing egress components will be required to comply with the requirements of the new occupant load.
Attention(STANDARD COMMENT) CONSTRUCTION SPLICES You are strongly encouraged to have any splices that may occur during this project, reviewed by CSFD. Failure to do so, can result in coordination issues that could prevent a final inspection from being completed, thus delaying the issuance of a Certificate of Occupancy.
Attention(STANDARD COMMENT) FIRE EXTINGUISHERS NOT REVIEWED PLAN REVIEWS DO NOT INCLUDE REVIEW OF TYPE, SIZE OR PLACEMENT OF FIRE EXTINGUISHERS. Fire extinguisher type, size and placement shall be in accordance with the requirements of the currently adopted International Fire Code and the current edition of NFPA 10. The general fire extinguisher requirement for commercial structures is met with a typical dry chemical fire extinguisher with a minimum of 2A10BC rating. If there are special hazards in this building there may be requirements for specific or different fire extinguishers and this should be discussed with the reviewer at Colorado Springs Fire Department. If the owner and/or occupant wishes to deviate from the fire extinguisher listed above, please contact your inspector and/or plan reviewer early in the project to avoid delays at the time of final.
FYI(STANDARD COMMENT) ADDRESSING: 2015 IFC 505.1; 2017 RBC 312 Address shall be posted on street addressed side of structure. Minimum 5" numbers with 1/2" stroke. Contrasting color to background. (2009 IFC 505.1)
FYI*****(STANDARD COMMENT) OCCUPANT LOAD THE OCCUPANT LOAD FOR THIS FACILITY IS:41 The occupant load, as approved by the Regional Building Department shall be posted in a visible location. This determined number shall not be exceeded under any circumstance.
FYI(STANDARD COMMENT) LOCKING HARDWARE: 2015 IFC 1010 All locking and latching devices shall comply with the requirements of the adopted building and fire code.
FYI*****(STANDARD COMMENT 10) SCHEDULING INSPECTIONS Please call 719-385-5982 Extension 2 to schedule all construction related inspection activities. Due to the dynamic nature of inspectors schedules, PLEASE call your inspection requests in with ample time to allow scheduling. When calling, please have your complete CSFD plan review number(s) ready for each inspection request. ( i.e. 2013-1234 - HS-1) The CSFD Approved sets of plans are to be on site for all inspections.
FYI*****(STANDARD COMMENT) DISAPPROVED ITEMS ADDRESSED The plans have been resubmitted and all the disapproved comments have been addressed and/or corrected as follows: 1. Per CO2 Questionnaire there will be no CO2 at all.
FYI(STANDARD COMMENT) RTP REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Roland Peterson Senior Fire Inspector, CSFD 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7369 roland.peterson@coloradosprings.gov
FYI(STANDARD COMMENT) REVIEWS: 2015 IFC 105.4.4 Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code.
FYI(STANDARD COMMENT) PERMITS Insure all applicable permits are obtained from the Regional Building Department and the Colorado Springs Fire Department for the work that is being done at this site.
4/27/2020 FYI*****(STANDARD COMMENT) This project is: Don Guillo, 2551 Delta Dr: interior remodel - expansion of tenant space Date of Plans: 3/25/20 You can access our web site for the latest fire department plan review comments: www.coloradosprings.gov search for Plan and Construction Review.
Disapproved(DISAPPROVED) CARBON DIOXIDE It appears that carbon dioxide will be used in this facility. Prior to approval of these plans we will need a CSFD CO2 declaration completed, signed, dated, and returned with construction set of plans. You fill find this enclosed or you can access it on our website. https://coloradosprings.gov/fire-department
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provide submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax, email or verbally.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. It is the responsibility of the design professional to conduct a complete re-review of the plans for additional violations of the adopted codes/standards and incorrect information prior to resubmitting.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) CLT REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Wyman "Chip" Taylor II, PE Fire Protection Engineer I 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7303 wtaylor@springsgov.com
4/9/2020 FYI*****(STANDARD COMMENT) This project is: Don Guillo, 2551 Delta Dr: interior remodel - expansion of tenant space Date of Plans: 3.25.2020 You can access our web site for the latest fire department plan review comments: www.coloradosprings.gov search for Plan and Construction Review.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. Address RBD comments regarding potential change of occupancy, etc. Unable to review due to questions regarding occupancy classifications. Also review the disapproved plans for additional written comments prior to submittal of new plans.
Disapproved(DISAPPROVED) CARBON DIOXIDE It appears that carbon dioxide will be used in this facility. Prior to approval of these plans we will need a CSFD CO2 declaration completed, signed, dated, and returned with construction set of plans. You fill find this enclosed or you can access it on our website. https://coloradosprings.gov/fire-department
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provide submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax, email or verbally.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) DEW REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Doreen "Dee" Withee, PE Fire Protection Engineer II, CSFD 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7361 dwithee@springsgov.com
FYI(STANDARD COMMENT) REVIEWS: 2015 IFC 105.4.4 Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code.


 

Contact Us: Email Us - Call: 385-CITY (719-385-2489) - RSS - Privacy, Linking and ADA Policies - designed, developed by projecta.com