NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING.

 System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.

DISPENSARY GROW SUITE 1105
01105 CHELTON RD

Review DateStatusComment(s)
2/24/2020 FYI*****(STANDARD COMMENT) This project is: Grow and Dispensary, 1105 S Chelton Rd: interior remodel change of occupancy from laundromat (B) to grow and dispensary (F1) Date of Plans: 1.31.2020 You can access our web site for the latest fire department plan review comments: www.coloradosprings.gov search for Plan and Construction Review.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. Doors 1 and 2: clarify how the electric strike is released? Please identify which code section you are complying with. 2. Provide occupant load so we can determine exit sign/emergency lighting requirements/compliance. Also review the disapproved plans for additional written comments prior to submittal of new plans.
Disapproved(DISAPPROVED) HAZARDOUS MATERIALS: Provide completed Hazarous Materials Operations Triage form for all Use/Dispensing/Storage of Hazardous Materials and Flammable Liquids that will be used within this facility. Provide an inventory list, including their uses and amounts, for all chemicals and/or compressed gases, you indicated Yes to on the HazMat Triage Form. List of chemicals to be categorized according to 2009 IFC Table 105.6.20. PLEASE INSURE YOU ANSWER ALL QUESTIONS AT THE BOTTOM OF THE FORMS, AND FILL OUT THE REQUESTED INFORMATION. All forms and packets are available at https://coloradosprings.gov/fire-department
Disapproved(DISAPPROVED) 'F' OCCUPANCIES Provide a detailed explanation of the products being manufactured, the process you use to fabricate your product, the products and components used to make the items that are manufactured. If there are hazardous materials used for this process, provide detailed information as is listed in our haz-mat HMMP requirements. What materials are stored within the structure, how they are stored, the heights the products are stored at, etc. The better the explanation, the easier it is for us to review and approve the plans.
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provide submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax, email or verbally.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) DEW REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Doreen "Dee" Withee, PE Fire Protection Engineer II, CSFD 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7361 dwithee@springsgov.com
FYI(STANDARD COMMENT) REVIEWS: 2015 IFC 105.4.4 Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code.


 

Contact Us: Email Us - Call: 385-CITY (719-385-2489) - RSS - Privacy, Linking and ADA Policies - designed, developed by projecta.com