RSS | Advanced Search | Site Map | Text Size a- A+
City of Colorado Springs
We Create Community

NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING.

 System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.

COLONEL MUSTARD SANDWICH SHOP
01412 21ST ST

Review DateStatusComment(s)
1/30/2020 ISPOKE WITH ARCHITECT R.J. STEER IN REGARDS TO CO2 QUESTIONNAIRE AND HE INDICATED ONLY BOTTLES AND CANS. INSPECTOR TO VERIFY NO BEVERAGE DISPENSING
FYI*****(STANDARD COMMENT) This project is: Colonel Mustard, 1412 W 21st St: interior remodel for a sandwich shop Date of Plans: 12.5.19 You can access our web site for the latest fire department plan review comments: www.coloradosprings.gov search for Plan and Construction Review.
FYI(STANDARD COMMENT) IMPACT TO EGRESS AND/OR FIRE PROTECTION SYSTEMS Egress components and fire protection systems that may be negatively impacted by your scope of work will be required to comply with the currently adopted fire code. As an example, if your work increases the occupant load of a space, the existing egress components will be required to comply with the requirements of the new occupant load.
Attention(STANDARD COMMENT) CONSTRUCTION SPLICES You are strongly encouraged to have any splices that may occur during this project, reviewed by CSFD. Failure to do so, can result in coordination issues that could prevent a final inspection from being completed, thus delaying the issuance of a Certificate of Occupancy.
Attention(STANDARD COMMENT) FIRE EXTINGUISHERS NOT REVIEWED PLAN REVIEWS DO NOT INCLUDE REVIEW OF TYPE, SIZE OR PLACEMENT OF FIRE EXTINGUISHERS. Fire extinguisher type, size and placement shall be in accordance with the requirements of the currently adopted International Fire Code and the current edition of NFPA 10. The general fire extinguisher requirement for commercial structures is met with a typical dry chemical fire extinguisher with a minimum of 2A10BC rating. If there are special hazards in this building there may be requirements for specific or different fire extinguishers and this should be discussed with the reviewer at Colorado Springs Fire Department. If the owner and/or occupant wishes to deviate from the fire extinguisher listed above, please contact your inspector and/or plan reviewer early in the project to avoid delays at the time of final.
FYI(STANDARD COMMENT) ADDRESSING - SUITE NUMBERS: 2015 IFC 505, 2017 RBC 312 Provide suite numbers as per the adopted fire code. MALLS/SHOPPING CENTERS: 4" high w/ 1/2" stroke and visible at 50 feet HOTEL ROOMS: 2" high with 1/4" stroke OFFICE SUITES: 2" high with 1/4" stroke REAR DOORS: 3" high with 3/8" stroke
FYI(STANDARD COMMENT) PREMISES IDENTIFICATION DURING CONSTRUCTION: 2017 RBC 312 Temporary address numbers shall be posted at the entrance to the construction site. The numbers shall be legible and visible from the street(s) or road(s) on which the building is addressed. The address numbers shall be at least 12 inches in height. Temporary signs may be made of wood, plastic, or metal. They shall be weather resistant and be maintained until replaced by permanent address numbers.
FYI*****(STANDARD COMMENT) OCCUPANT LOAD THE OCCUPANT LOAD FOR THIS FACILITY IS: 17 The occupant load, as approved by the Regional Building Department shall be posted in a visible location. This determined number shall not be exceeded under any circumstance.
FYI(STANDARD COMMENT) EMERGENCY LIGHTING AND EXIT SIGNS: 2015 IFC 1008, 1013 Exit Signs and Emergency Lighting shall be in compliance with the adopted building and fire code. Paths of egress will be verified to be compliant, even if they are beyond the scope of work. If your scope of work impacts the means of egress, i.e. a new conference room - the path of egress beyond that scope of work will be verified to make sure occupants can safely egress the building.
FYI(STANDARD COMMENT) LOCKING HARDWARE: 2015 IFC 1010 All locking and latching devices shall comply with the requirements of the adopted building and fire code. 1. FRONT MAIN ENTRY CAN HAVE DOUBLE KEYED INDICATING LOCK WITH SIGNAGE AND REAR DOOR WILL BE REQUIRED TO HAVE SINGLE ACTION HARDWARE WITH NO BOLTS.
FYI*****(STANDARD COMMENT 10) SCHEDULING INSPECTIONS 2019 Fee Schedule, --2--- inspections/ --1.5--- hours (Note: Inspection time is not transferrable) Please call 719-385-5982 Extension 2 to schedule all construction related inspection activities. Due to the dynamic nature of inspectors schedules, PLEASE call your inspection requests in with ample time to allow scheduling. When calling, please have your complete CSFD plan review number(s) ready for each inspection request. ( i.e. 2013-1234 - HS-1) The CSFD Approved sets of plans are to be on site for all inspections.
FYI*****(STANDARD COMMENT) DISAPPROVED ITEMS ADDRESSED The plans have been resubmitted and all the disapproved comments have been addressed and/or corrected as follows: 1. Incomplete submittal: provide kitchen equipment schedule - without this we cannot determine if any kitchen suppression systems are or are not required. KITCHEN EQUIPMENT SUBMITTED DOES NOT SHOW ANY APPLIANCE THAT WOULD REQUIRE FIRE SUPPRESSION OR A TYPE I HOOD 2. ENUMERATIONS APPROVED.
FYI(STANDARD COMMENT) JAH REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Jeff Hanenberg Senior Fire Code Inspector 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7359 jeff.hanenberg@coloradosprings.gov
FYI(STANDARD COMMENT) REVIEWS: 2015 IFC 105.4.4 Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code.
FYI(STANDARD COMMENT) PERMITS Insure all applicable permits are obtained from the Regional Building Department and the Colorado Springs Fire Department for the work that is being done at this site.
1/2/2020 FYI*****(STANDARD COMMENT) This project is: Colonel Mustard, 1412 W 21st St: interior remodel for a sandwich shop Date of Plans: 12.5.19 You can access our web site for the latest fire department plan review comments: www.coloradosprings.gov search for Plan and Construction Review.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. Incomplete submittal: provide kitchen equipment schedule - without this we cannot determine if any kitchen suppression systems are or are not required. Also review the disapproved plans for additional written comments prior to submittal of new plans.
Disapproved(DISAPPROVED) TEMPORARY ADDRESS A temporary address has been assigned to these plans. CSFD will not approve the construction plans until the Regional Building Department Enumerations Office has assigned a permanent address to this facility, and has approved the construction plans.
Disapproved(DISAPPROVED) MULTI-TENANT BUILDINGS It appears this building will or does incorporate more than one tenant. As such, Enumerations requires secondary addressing for all tenant spaces. Provide a floor plan for each level or affected level of the building, clearing indicating each separate unit. Be sure to include the street address(es) for this location on the plan.
Disapproved(DISAPPROVED) CARBON DIOXIDE It appears that carbon dioxide will be used in this facility. Prior to approval of these plans we will need a CSFD CO2 declaration completed, signed, dated, and returned with construction set of plans. You fill find this enclosed or you can access it on our website. https://coloradosprings.gov/fire-department
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provide submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax, email or verbally.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) DEW REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Doreen "Dee" Withee, PE Fire Protection Engineer II, CSFD 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7361 dwithee@springsgov.com
FYI(STANDARD COMMENT) REVIEWS: 2015 IFC 105.4.4 Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code.


 

Contact Us: Email Us - Call: 385-CITY (719-385-2489) - RSS - Privacy, Linking and ADA Policies - designed, developed by projecta.com