NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING.

 System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.

COLLINS AEROSPACE SYSTEMS
01275 NEWPORT RD

Review DateStatusComment(s)
2/21/2020 FYI*****(STANDARD COMMENT) This project is: Collins Aerospace 1275 Newport Rd, Sprinkler Pipe Replacement This plan review is based on the requirements found within the adopted Editions of the International Building Code, International Fire Code and the related Standards.
FYI*****(STANDARD COMMENT) REVISION: Scope of Revision: Addition of sprinkler heads and relocating of branchline to correct red line comments from review of system 3 pipe replacement. Date of Revision: 2/5/20 This review is limited to areas clouded and/or indicated as changed. Permit release for this splice or revision does not include other plan elements even if revised from prior submissions.
FYI(STANDARD COMMENT) CLT REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Wyman "Chip" Taylor II, PE Fire Protection Engineer I 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7303 wtaylor@springsgov.com
1/30/2020 FYI*****(STANDARD COMMENT) This project is: Collins Aerospace 1275 Newport Rd, Sprinkler Pipe Replacement This plan review is based on the requirements found within the adopted Editions of the International Building Code, International Fire Code and the related Standards.
FYI*****(STANDARD COMMENT) The fire sprinkler system is being installed by: JCFP CSFD does not allow any combustibles into a building until a sprinkler system has passed it's final acceptance test performed by CSFD Inspector's.
FYI*****(STANDARD COMMENT) SPRINKLER SYSTEM DESIGN CRITERIA: Type of System: NFPA 13 Wet Type of head (s): 5.6K QR Pend; 5.6K UR Design Criteria: .20/1500 Adjustments:
FYI*****(STANDARD COMMENT) REVISION: Scope of Revision: Add system 3 to the scope of pipe replament Date of Revision: 1/16/20 This review is limited to areas clouded and/or indicated as changed. Permit release for this splice or revision does not include other plan elements even if revised from prior submissions.
Approved/Corrected*****(STANDARD COMMENT) RED-LINED COMMENTS The following RED-LINED items are to be corrected prior to final inspection: 1. Branch Line east of Column line 23 needs to be moved to the west so that it is not overspaced off of column line 23. 2. Upright sprinkler heads are overspaced to full height walls shown on plans
FYI(STANDARD COMMENT) LICENSED INSTALLER/SERVICE TECHNICIAN An On-Site Installer/Service TechniciaN shall supervise all on-site work on any fire protection system. This On-Site Installer shall have a current Installer Certificate (RBD Wallet Card), on his/her person, while on the job site.
FYI(STANDARD COMMENT) CONCEALED SPACES - This plan did not provide any information on combustible concealed spaces. NFPA 13 requires that "All concealed spaces enclosed wholly or partially by exposed combustible construction shall be protected by sprinklers". There are several specific allowances to this section that allow for the omission of sprinklers. If there are combustible concealed areas found during the installation of the system that do not meet the requirements of the NFPA 13, then these areas will be required to be sprinkled. (NFPA 13:8.15.1) IT IS THE RESPONSIBILITY OF THE INSTALLER TO MAKE SURE THAT THE SYSTEM IS INSTALLED IN ACCORDANCE WITH THE STANDARD.
FYI(STANDARD COMMENT) FREEZING CONDITIONS It is the designer's responsibility to provide the building owner with a system design that will continue to function reliably even under adverse temperature conditions. The sprinkler contractor must be conscious of field conditions that may affect the performance of their system, such as drafts, disturbed insulation, installation along exterior walls, etc. and incorporate such conditions into a reliable design.
Attention(STANDARD COMMENT) CERTIFICATE OF INSTALLATION: It is the installer's responsibility to certify through this form (attached to the plans) that the system has been properly installed and tested. NOTE! CSFD will no longer be providing these forms as they are now available online at: https://coloradosprings.gov/sites/default/files/inline-images/installer_certificaiton.xlsx The form is to be filled out in its entirety PRIOR TO THE ARRIVAL OF THE FIRE INSPECTOR conducting the final inspection and/or acceptance test of the system. FINAL INSPECTIONS WILL NOT BE CONDUCTED WITHOUT THIS FORM BEING COMPLETED.
FYI(STANDARD COMMENT) AS-BUILT PLANS All deviations from approved plans shall be documented and submitted to CSFD for archival. Reviews will not be conducted on as-builts, as these field changes are often verified as compliant by the fire inspectors. All as-built plans shall be conspicuously marked as such. Any changes requiring approval prior to Final shall be submitted as a REVISION.
Attention*****(STANDARD COMMENT) SCHEDULING INSPECTIONS 2019 Fee Schedule, --3--- inspections/ ----- hours (Inspection time is not transferrable) Please call 719-385-5982 Extension 2 to schedule all construction related inspection activities. Due to the dynamic nature of inspectors schedules, PLEASE call your inspection requests in with ample time to allow scheduling. When calling, please have your complete CSFD plan review number(s) ready for each inspection request. ( i.e. 2013-1234 - HS-1) The CSFD Approved sets of plans are to be on site for all inspections.
FYI(STANDARD COMMENT) ROUGH VISUAL INSPECTIONS: Rough Visual inspections shall be completed PRIOR TO any bucket tests or final inspections.
FYI(STANDARD COMMENT) CONCEALED WORK: The fire sprinkler piping shall not be covered up by walls, sheetrock, ceiling tiles, etc... prior to the CSFD visual inspections of the piping. If the piping is covered, and the inspectors cannot inspect it as is required by Fire Code, the walls,sheetrock, ceiling tiles, etc... will be required to be removed. If this means that finished ceilings will need to be removed, this will be required to be done! (IFC 106.3)
FYI(STANDARD COMMENT) PLAN REVIEW/PERMIT FEES: All fire department fees are to be paid prior to issuance of any permits. These fees must be paid directly to the Colorado Springs Fire Department - Development Review Enterprise - at 2880 International Circle - Suite 200-7.
FYI(STANDARD COMMENT) REVIEWS: Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirement are met as established by the Authority Having Jurisdiction, whether of not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the fire code requirements of the 2003 International Fire Code, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)
FYI(STANDARD COMMENT) CLT REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Wyman "Chip" Taylor II, PE Fire Protection Engineer I 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7303 wtaylor@springsgov.com
1/13/2020 FYI*****(STANDARD COMMENT) This project is: Collins Aerospace 1275 Newport Rd, Sprinkler Pipe Replacement This plan review is based on the requirements found within the adopted Editions of the International Building Code, International Fire Code and the related Standards.
FYI*****(STANDARD COMMENT) REVISION: Scope of Revision: Add pipe replacement of system 3 to scope of work Date of Revision: 12/30/19 This review is limited to areas clouded and/or indicated as changed. Permit release for this splice or revision does not include other plan elements even if revised from prior submissions.
FYI(STANDARD COMMENT) CLT REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Wyman "Chip" Taylor II, PE Fire Protection Engineer I 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7303 wtaylor@springsgov.com
Disapproved*****(STANDARD COMMENT) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. Correct hydraulic nodes between node 626 and node 1 on plans, so that they correspond to the nodes in the hydraulic calculations. 2. Are flex drops being used? Plans do not indicate flex drops are being used, and there was not a hydraulic calulcation provided showing that they will work hdraulically. Either provide information on flex drops on your plans and a proof calculation showing that they will work, or remove product data for this item. 3. Tail back sprinkler heads off the main are overspaced. These heads cannot exceeed 4'-4" off walls to remain below 130 sq ft head spacing. 4. SE office area is shown surrounded by full height walls. Upright sprinklers in the main manufacturing area are overspaced to these ful height walls. 5. Plans do not show difuser locations. Confirm that office heads next to difusers will be intermedicate temperature. Also review the disapproved plans for additional written comments prior to submittal of new plans.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. It is the responsibility of the design professional to conduct a complete re-review of the plans for additional violations of the adopted codes/standards and incorrect information prior to resubmitting.
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provide submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax, email or verbally.
11/1/2019 FYI*****(STANDARD COMMENT) This project is: Collins Aerospace 1275 Newport Rd, Sprinkler Pipe Replacement This plan review is based on the requirements found within the adopted Editions of the International Building Code, International Fire Code and the related Standards.
FYI*****(STANDARD COMMENT) SPRINKLER SYSTEM DESIGN CRITERIA: Type of System: WET Type of head (s): K11.2 200 degree Design Criteria: OHII Adjustments:NONE
FYI*****(STANDARD COMMENT) REMODEL SCOPE OF WORK: Area/scope of work is 474----- SPRINKLERS IN AREA -----1 & 2 as marked on plans-------of the building. Flex Connections: NO Brand: Equivalent Length: UL 2443/FM 1637 Complaint: Heat Trace: -NO---- Brand: -----
FYI(STANDARD COMMENT) FLEXIBLE SPRINKLER CONNECTIONS AND HEAT TRACE: Flex Connections: Yes Brand: Victaulic Equivalent Length: 22' UL 2443/FM 1637 Complaint: Yes Heat Trace: NO Brand: -----
FYI(STANDARD COMMENT) LICENSED INSTALLER/SERVICE TECHNICIAN An On-Site Installer/Service TechniciaN shall supervise all on-site work on any fire protection system. This On-Site Installer shall have a current Installer Certificate (RBD Wallet Card), on his/her person, while on the job site.
FYI(STANDARD COMMENT) CONCEALED SPACES - This plan did not provide any information on combustible concealed spaces. NFPA 13 requires that "All concealed spaces enclosed wholly or partially by exposed combustible construction shall be protected by sprinklers". There are several specific allowances to this section that allow for the omission of sprinklers. If there are combustible concealed areas found during the installation of the system that do not meet the requirements of the NFPA 13, then these areas will be required to be sprinkled. (NFPA 13:8.15.1) IT IS THE RESPONSIBILITY OF THE INSTALLER TO MAKE SURE THAT THE SYSTEM IS INSTALLED IN ACCORDANCE WITH THE STANDARD.
FYI(STANDARD COMMENT) FREEZING CONDITIONS It is the designer's responsibility to provide the building owner with a system design that will continue to function reliably even under adverse temperature conditions. The sprinkler contractor must be conscious of field conditions that may affect the performance of their system, such as drafts, disturbed insulation, installation along exterior walls, etc. and incorporate such conditions into a reliable design.
Attention(STANDARD COMMENT) CERTIFICATE OF INSTALLATION: It is the installer's responsibility to certify through this form (attached to the plans) that the system has been properly installed and tested. NOTE! CSFD will no longer be providing these forms as they are now available online at: https://coloradosprings.gov/sites/default/files/inline-images/installer_certificaiton.xlsx The form is to be filled out in its entirety PRIOR TO THE ARRIVAL OF THE FIRE INSPECTOR conducting the final inspection and/or acceptance test of the system. FINAL INSPECTIONS WILL NOT BE CONDUCTED WITHOUT THIS FORM BEING COMPLETED.
FYI(STANDARD COMMENT) AS-BUILT PLANS All deviations from approved plans shall be documented and submitted to CSFD for archival. Reviews will not be conducted on as-builts, as these field changes are often verified as compliant by the fire inspectors. All as-built plans shall be conspicuously marked as such. Any changes requiring approval prior to Final shall be submitted as a REVISION.
Attention*****(STANDARD COMMENT) SCHEDULING INSPECTIONS 2019 Fee Schedule, --3--- inspections/ --6--- hours (Inspection time is not transferrable) Please call 719-385-5982 Extension 2 to schedule all construction related inspection activities. Due to the dynamic nature of inspectors schedules, PLEASE call your inspection requests in with ample time to allow scheduling. When calling, please have your complete CSFD plan review number(s) ready for each inspection request. ( i.e. 2013-1234 - HS-1) The CSFD Approved sets of plans are to be on site for all inspections.
FYI(STANDARD COMMENT) ROUGH VISUAL INSPECTIONS: Rough Visual inspections shall be completed PRIOR TO any bucket tests or final inspections.
FYI(STANDARD COMMENT) CONCEALED WORK: The fire sprinkler piping shall not be covered up by walls, sheetrock, ceiling tiles, etc... prior to the CSFD visual inspections of the piping. If the piping is covered, and the inspectors cannot inspect it as is required by Fire Code, the walls,sheetrock, ceiling tiles, etc... will be required to be removed. If this means that finished ceilings will need to be removed, this will be required to be done! (IFC 106.3)
FYI(STANDARD COMMENT) PLAN REVIEW/PERMIT FEES: All fire department fees are to be paid prior to issuance of any permits. These fees must be paid directly to the Colorado Springs Fire Department - Development Review Enterprise - at 2880 International Circle - Suite 200-7.
FYI(STANDARD COMMENT) REVIEWS: Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirement are met as established by the Authority Having Jurisdiction, whether of not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the fire code requirements of the 2003 International Fire Code, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)
FYI(STANDARD COMMENT) RTP REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Roland Peterson Senior Fire Inspector, CSFD 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7369 rpeterson@springsgov.com
FYI*****(STANDARD COMMENT) DISAPPROVED ITEMS ADDRESSED: The plans have been resubmitted and all the disapproved comments have been addressed and/or corrected as follows: 1. K8 heads have all been switched to K11.2 eliminating calc 4, and other issues. 2. K11.2 heads have been provided with teh appropriate gpm and psi for 18' x 18' spacing.
10/16/2019 FYI*****(STANDARD COMMENT) This project is: Collins Aerospace 1275 Newport Rd, Sprinkler Pipe Replacement This plan review is based on the requirements found within the adopted Editions of the International Building Code, International Fire Code and the related Standards.
FYI*****(STANDARD COMMENT) The fire sprinkler system is being installed by: JOHNSON CONTROLS CSFD does not allow any combustibles into a building until a sprinkler system has passed it's final acceptance test performed by CSFD Inspector's.
FYI(STANDARD COMMENT) REVIEWS: Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirement are met as established by the Authority Having Jurisdiction, whether of not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the fire code requirements of the 2003 International Fire Code, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)
FYI(STANDARD COMMENT) DEW REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Doreen "Dee" Withee, PE Fire Protection Engineer II, CSFD 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7361 dwithee@springsgov.com
Disapproved*****(STANDARD COMMENT) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. Remote #3: heads noted are VK602 K=8.0 - this area was calculated such that each head is flowing 25 gpm at 9.76 si. This criteria isn't supported by the cut sheet provided for this head for either UL or FM approval. Per the cut sheet the smallest protection area is 16x16 and 26 gpm @ 10.7 psi. These heads are spaced at aproximately 12-6x10 which is not an EC coverage area? Reconcile discrepancies. 2. Remote #3: the branchlines and transition to the next type of head is confusing - is there piping/fittings covered by the hydraulic area outline? Is there a room that is hidden? This also appears to be introducing heads of varying k-factors in the same area. Please clarify what is going on here. 3. Remote #4: Hydraulic calculations and plans do not match - Hydraulics state these heads are covering 130 sqft per head, but the plans show these heads to be protecting closer to 256 sqft. NOTE: the fire flow information is over 1 year old, however I will accept the report since the project was submitted prior to and reviews began before the 1-year expiration date. Also review the disapproved plans for additional written comments prior to submittal of new plans.
9/5/2019 FYI*****(STANDARD COMMENT) This project is: Collins Aerospace 1275 Newport Rd, Sprinkler Pipe Replacement This plan review is based on the requirements found within the adopted Editions of the International Building Code, International Fire Code and the related Standards.
FYI*****(STANDARD COMMENT) WORK AT RISK: On --9/5/19--- approval was granted by --FPE Taylor---- for sprinkler work to begin by --JCFP--- without approved plans or permits. Any changes or modification required through plan review will be required. No inspections will be conducted without approved plans and permits.
9/3/2019 FYI*****(STANDARD COMMENT) This project is: Collins Areospace 1275 Newport Rd, Sprinkler Pipe Replacement This plan review is based on the requirements found within the adopted Editions of the International Building Code, International Fire Code and the related Standards.
FYI(STANDARD COMMENT) CLT REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Wyman "Chip" Taylor II, PE Fire Protection Engineer I 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7303 wtaylor@springsgov.com
Disapproved*****(STANDARD COMMENT) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. Heads in existing calculations are not shown meeting the required gpm and psi as required per cut sheets for the EC-11 heads for OH II. 2. Ensure that all hydraulic nodes are shown on plans to allow reviewer to verify existing calculations. 3. Provide riser diagram with hydraulic nodes. Is the riser and zone valves being replaced? If so, provide cut sheets for these items. 4. Provide site plan showing underground pipe routing, pipe size and lengths, hydraulic nodes, and test hydrant. 5. What is the roof slope of the building? 6. What edition of NFPA 13, was this system installed under? 7. Provide letter on JCFP's letterhead stating that you have surveyed the existing building, and that the current system design meets the hazard currently present in the building. 8. FP-2 shows remote areas that exceed OH II density. The EC-11 heads are not listed for any hazard greater that OH II. 9. RME must sign all sheets of the plans. 10. Review Stopped! No review of hydraulic calculations has been performed. Also review the disapproved plans for additional written comments prior to submittal of new plans.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. It is the responsibility of the design professional to conduct a complete re-review of the plans for additional violations of the adopted codes/standards and incorrect information prior to resubmitting.
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provide submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax, email or verbally.


 