NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING.

 System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.

ADVANCE CONCRETE
03570 AEROSPACE BLVD

Review DateStatusComment(s)
5/20/2020 FYI*****(STANDARD COMMENT) This project is: Advance Concrete, 3570 Aerospace Blvd, New Warehouse - commercial truck bed manufactuing Date of Plans:e-plan 5-11-2020 You can access our web site for the latest fire department plan review comments: www.coloradosprings.gov search for Plan and Construction Review.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. All hazmat, high pile, F and S Occupancy documents must be uploaded with electronic submittal. 2. Provide emergency lighting in warehouse and office space. Also review the disapproved plans for additional written comments prior to submittal of new plans.
Disapproved(DISAPPROVED)) HIGH PILE STORAGE Based upon a review of the construction plans, it has been determined that this facility is capable of storing high-pile stock. If you are NOT planning on storing ordinary combustibles over 12-feet (or over 6-ft for high-hazard combustibles) then the owners must complete the NO STACKING AGREEMENT and HIGH PILE STORAGE QUESTIONNAIRE attach it to the construction plans prior to submitting the plans for a fire department re-review. However, if you ARE planning on storing combustibles over the allowable limits, you will need to attach the "CSFD High-Pile Questionnaire" to the plans. All forms and packets are available at https://coloradosprings.gov/fire-department
Disapproved(DISAPPROVED) HAZARDOUS MATERIALS: Provide completed Hazarous Materials Operations Triage form for all Use/Dispensing/Storage of Hazardous Materials and Flammable Liquids that will be used within this facility. Provide an inventory list, including their uses and amounts, for all chemicals and/or compressed gases, you indicated Yes to on the HazMat Triage Form. List of chemicals to be categorized according to 2009 IFC Table 105.6.20. PLEASE INSURE YOU ANSWER ALL QUESTIONS AT THE BOTTOM OF THE FORMS, AND FILL OUT THE REQUESTED INFORMATION. All forms and packets are available at https://coloradosprings.gov/fire-department
Disapproved(DISAPPROVED) 'F' OCCUPANCIES Provide a detailed explanation of the products being manufactured, the process you use to fabricate your product, the products and components used to make the items that are manufactured. If there are hazardous materials used for this process, provide detailed information as is listed in our haz-mat HMMP requirements. What materials are stored within the structure, how they are stored, the heights the products are stored at, etc. The better the explanation, the easier it is for us to review and approve the plans.
Disapproved(DISAPPROVED) 'S' OCCUPANCIES Provide a detailed explanation of the exact types of work being done in this facility. Clearly state if there will be welding, or automotive repair within this facility. If there are hazardous materials used for this process, provide detailed information as is listed in our haz-mat HMMP requirements. Fill out and submit our "Hazardous Materials Permit Amount Certification Form." Your haz-mat must be under the exempt amounts for this facility to be considered as a S occupancy.
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provide submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax, email or verbally.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. It is the responsibility of the design professional to conduct a complete re-review of the plans for additional violations of the adopted codes/standards and incorrect information prior to resubmitting.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) RTP REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Roland Peterson Senior Fire Inspector, CSFD 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7369 roland.peterson@coloradosprings.gov
FYI(STANDARD COMMENT) REVIEWS: 2015 IFC 105.4.4 Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code.
6/20/2019 FYI*****(STANDARD COMMENT) This project is: Advance Concrete, 3570 Aerospace Blvd, New Warehouse - commercial truck bed manufactuing Date of Plans: 11.16.18 You can access our web site for the latest fire department plan review comments: www.coloradosprings.gov search for Plan and Construction Review.
FYI*****ADDITIONAL FEES: This is our --2nd---, review of these plans. Any and all future plan submittals for this specific permit will have additional plan review fees charged to the project, as per the approved fee schedule.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: OUTSTANDING ITEMS FROM PREVIOUS REIVEW: 1. WATER PLAN APPROVAL OR FIRE FLOW REPORT FOR EXISTING HYDRANTS FROM CSU. 2. HIGH PILE STORAGE - NO STACKING WAIVER. Not all materials can be stored up to 12-feet, some are limited to 6-feet. You must provide a signed no stacking waiver (a copy has been provided in the plans) indicating your desire to comply with storage requriements. Also review the disapproved plans for additional written comments prior to submittal of new plans.
Disapproved*****(DISAPPROVED) SITE PLANS: To help us ensure adequate access has been provided to this proposed structure, please provide the following: --XXX-- Approved Development Plan - THE APPROVED DEVELOMENT PLAN MUST BE INCLUDED WITH THE BUILDING PERMIT PLAN SET.
Disapproved*****(DISAPPROVED) WATER SUPPLIES To help us ensure there is adequate exterior fire protection, please provide the following: -XXX---- Approved Water Plan (mains, hydrants, etc. for new structures in green field development) OR --XXX--- Fire flow report from CSU with map (where there is no new hydrants and/or this is a an infill project. You can requestion one here: https://www.csu.org/Pages/construction-drawing-review.aspx IF YOU ARE NOT ADDING ANY NEW FIRE HYDRANTS FOR THIS STRUCTURE, THEN PLEASE PROVIDE THE FIRE FLOW REPORT FOR THE EXISTING FIRE HYDRANTS. IF NEW HYDRANTS ARE BEING ADDED, CSFD MUST REVIEW AND APPROVE THE WATER PLANS PRIOR TO SIGNATURE REQUESTS ON THOSE PLANS. COPIES OF APPROVED AND SIGNED WATER PLANS SHALL BE INCLUCED IN THE BUILDING PERMIT PLANS.
Disapproved(DISAPPROVED)) HIGH PILE STORAGE Based upon a review of the construction plans, it has been determined that this facility is capable of storing high-pile stock. If you are NOT planning on storing ordinary combustibles over 12-feet (or over 6-ft for high-hazard combustibles) then the owners must complete the NO STACKING AGREEMENT and HIGH PILE STORAGE QUESTIONNAIRE attach it to the construction plans prior to submitting the plans for a fire department re-review. However, if you ARE planning on storing combustibles over the allowable limits, you will need to attach the "CSFD High-Pile Questionnaire" to the plans. All forms and packets are available at https://coloradosprings.gov/fire-department
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provide submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax, email or verbally.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) DEW REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Doreen "Dee" Withee, PE Fire Protection Engineer II, CSFD 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7361 dwithee@springsgov.com
FYI(STANDARD COMMENT) REVIEWS: 2015 IFC 105.4.4 Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code.
4/9/2019 FYI*****(STANDARD COMMENT) This project is: Advance Concrete, 3570 Aerospace Blvd, New Warehouse Date of Plans:11/16/2018 You can access our web site for the latest fire department plan review comments: www.coloradosprings.gov search for Plan and Construction Review.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1.The hazmat triage form does not state if the quantities are above or below permit levels. Also review the disapproved plans for additional written comments prior to submittal of new plans.
Disapproved*****(DISAPPROVED) WATER SUPPLIES To help us ensure there is adequate exterior fire protection, please provide the following: --X--- Approved Water Plan (mains, hydrants, etc. for new structures in green field development) ----- Approved Utility Service Plan (domestic and/or fire service lines, with existing infrastructure) ----- Fire flow report from CSU with map (where there is no new hydrants and/or this is a an infill project. You can requestion one here: https://www.csu.org/Pages/construction-drawing-review.aspx
Disapproved(DISAPPROVED)) HIGH PILE STORAGE Based upon a review of the construction plans, it has been determined that this facility is capable of storing high-pile stock. If you are NOT planning on storing ordinary combustibles over 12-feet (or over 6-ft for high-hazard combustibles) then the owners must complete the NO STACKING AGREEMENT and HIGH PILE STORAGE QUESTIONNAIRE attach it to the construction plans prior to submitting the plans for a fire department re-review. However, if you ARE planning on storing combustibles over the allowable limits, you will need to attach the "CSFD High-Pile Questionnaire" to the plans. All forms and packets are available at https://coloradosprings.gov/fire-department
Disapproved(DISAPPROVED) 'F' OCCUPANCIES Provide a detailed explanation of the products being manufactured, the process you use to fabricate your product, the products and components used to make the items that are manufactured. If there are hazardous materials used for this process, provide detailed information as is listed in our haz-mat HMMP requirements. What materials are stored within the structure, how they are stored, the heights the products are stored at, etc. The better the explanation, the easier it is for us to review and approve the plans.
Disapproved(DISAPPROVED) 'S' OCCUPANCIES Provide a detailed explanation of the exact types of work being done in this facility. Clearly state if there will be welding, or automotive repair within this facility. If there are hazardous materials used for this process, provide detailed information as is listed in our haz-mat HMMP requirements. Fill out and submit our "Hazardous Materials Permit Amount Certification Form." Your haz-mat must be under the exempt amounts for this facility to be considered as a S occupancy.
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provide submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax, email or verbally.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. It is the responsibility of the design professional to conduct a complete re-review of the plans for additional violations of the adopted codes/standards and incorrect information prior to resubmitting.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) RTP REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Roland Peterson Senior Fire Inspector, CSFD 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7369 rpeterson@springsgov.com
FYI(STANDARD COMMENT) REVIEWS: 2015 IFC 105.4.4 Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code.


 