NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING.

 System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.

CSU 33RD STREET PUMP STATION
03315 COLORADO AVE

Review DateStatusComment(s)
4/27/2020 FYI*****(STANDARD COMMENT) This project is: CSU 33rd Street Pump Station, 3315 W Colorado Ave, New Pump Station Date of Plans: 1/15/20 You can access our web site for the latest fire department plan review comments: www.coloradosprings.gov search for Plan and Construction Review.
Disapproved*****(DISAPPROVED) WATER SUPPLIES To help us ensure there is adequate exterior fire protection, please provide the following: --XX--- Approved Water Plan (mains, hydrants, etc. for new structures in green field development)
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provide submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax, email or verbally.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. It is the responsibility of the design professional to conduct a complete re-review of the plans for additional violations of the adopted codes/standards and incorrect information prior to resubmitting.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) CLT REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Wyman "Chip" Taylor II, PE Fire Protection Engineer I 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7303 wtaylor@springsgov.com
2/27/2020 ApprovedPrevious review comments not addressed
2/6/2020 FYI*****(STANDARD COMMENT) This project is: CSU 33rd Street Pump Station, 3315 W Colorado Ave, New Pump Station Date of Plans: 1/15/19 You can access our web site for the latest fire department plan review comments: www.coloradosprings.gov search for Plan and Construction Review.
Disapproved*****(DISAPPROVED) WATER SUPPLIES To help us ensure there is adequate exterior fire protection, please provide the following: ---XX-- Approved Water Plan (mains, hydrants, etc. for new structures in green field development)
Disapproved(DISAPPROVED) HAZARDOUS MATERIALS: Provide completed Hazarous Materials Operations Triage form for all Use/Dispensing/Storage of Hazardous Materials and Flammable Liquids that will be used within this facility. Provide an inventory list, including their uses and amounts, for all chemicals and/or compressed gases, you indicated Yes to on the HazMat Triage Form. List of chemicals to be categorized according to 2009 IFC Table 105.6.20. PLEASE INSURE YOU ANSWER ALL QUESTIONS AT THE BOTTOM OF THE FORMS, AND FILL OUT THE REQUESTED INFORMATION. All forms and packets are available at https://coloradosprings.gov/fire-department
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provide submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax, email or verbally.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. It is the responsibility of the design professional to conduct a complete re-review of the plans for additional violations of the adopted codes/standards and incorrect information prior to resubmitting.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) CLT REVIEWER CONTACT: If you have any specific questions or concerns about these comments, please feel free to contact me at: Wyman "Chip" Taylor II, PE Fire Protection Engineer I 2880 International Circle, Suite 200-7 Colorado Springs, CO 80910 (T) 719-385-7303 wtaylor@springsgov.com


 