Colorado Springs Fire Department
Public Safety Sales Tax (PSST)
2002 through 2012
Public Safety Sales Tax (PSST)
2002 through 2012
PSST Capital Projects Overview
| Completed Projects | ||||
| Original Project Budget | Modified Budget | Final Cost | Completion | |
| Police Evidence Building, Phase II | $460,000 | NA | $475,000 | Completed June 2002 |
| Acacia |
$190,000 |
NA |
$145,000 |
Completed August 2002 |
| Fire |
$1,730,000 |
NA |
$1,658,481 |
Completed October 2002 |
| Fire Station 14 Relocation | $2,911,000 | NA | $2,532,861 |
Completed July 2003 |
| Police Helicopter Hangar, Phase II | $200,000 | NA | $191,000 | Completed Summer 2003 |
| Fire Station 19 | $2,911,000 |
NA |
$2,763,195 |
Completed February 2004 |
| Police Substation - 4th Division Stetson Hills | $4,275,000 | $6,275,000 | $6,430,000 |
Completed May 2004 |
| Fire Station Health, Safety & Accessibility Compliance Study | $270,000 | $286,443 | $212,685 |
Completed September 2004 |
| Fire Station 20 | $2,911,000 | NA | $2,924,865 | Completed November 2004 |
| Fire |
$1,200,000 | $1,477,768 | $1,477,141 |
Completed September 2005 |
| Fire Station 6 Renovation & HazMat Storage | $750,000 | $177,201 | $122,324 |
Completed September 2006 |
| Fire Department Complex, Phase IIA (FDC West) | $6,163,850 | $2,250,000 | $2,351,306 |
Completed August 2008 |
| Fire Station 8 Renovation | $1,433,000 | $4,632,860 | $4,494,082 |
Completed August 2008 |
| Fire Station 17, Phase II | $980,000 | NA | $191,471 | Completed August 2008 |
| Police Substation - Gold Hill Div./POC Renovation | $4,625,000 | $7,464,261 | $7,372,304 |
Completed January 2009 |
|
Projects to be Completed | |||||
| Original Project Budget | Modified Budget | Final Cost | Start Date | End Date | |
| Ventilation Improvement in Fire Stations | $450,000 | $1,958,547 | Open | March 2005 | TBD |
| Fire Department Complex, Phase IIB (future new construction) | $6,163,850 | $5,202,500 | Open | TBD | TBD |
| Fire Station 1 Replacement/Renovation | $4,456,053 | $6,439,934 | Open | TBD | TBD |
| Fire Station 21 | $2,911,000 | $5,271,692 | Open | TBD | TBD |
| Fire Station, Land Acquisition | $564,445 | ||||
| Police Substation - 5th Division, Land Acquisition | $950,000 |
|
| ||